Hi ILF, Please see communication we received from Jodan Construction 28 August 2017. Update of the Cedar Road project Firstly the recording of Tshepo Marakala that was placed on the social media by Marnelle was far from accurate. Jodan construction managed to file a court interdict against Tshepo and five others on Friday the 25…

Please see information from the CPF regarding protests taking place this weekend, please plan your routes accordingly. The following information was provided by SAPS Douglasdale regarding two marches set to occur in the Douglasdale area on Saturday the 26th of August: MARCH PROTESTING CRIMES AGAINST WOMEN AND CHILDREN. Commencing at Cedar Square at 09:00 and…

We were informed telephonically today that Jodan Construction are not going to release any statements to us until their court order. Residents, businesses and employees are severely suffering the consequences of this road upgrade and it is actually unacceptable. We all understand the importance of the upgrade and are looking forward to the completed project.…

This is a collective post regarding taxi’s and general motor vehicles as there is OUTRAGE regarding traffic and law breaking in the area at the moment! Firstly lets touch on the Cedar Road Upgrade: There was a video posted to the group about taxi’s driving on the new part of Cedar Road which is still…

Hi ILF, Please see direct communications from Jodan Construction on the Road Upgrade. Good day to all I hear and see frustrations’ are running high. Hopefully I can give you all some good news. Our progress is as follows: The road between Stinkwood and Lombardy will open on Monday and let`s hope this will ease…

Message from Jodan Construction: Good day to all Some good news, the intersection to the hospital is complete on the hospital side and this should ease up the traffic flow tomorrow when we open the new road from Campbell road to Cedar Ave West. Construction will take place on Stinkwood intersection tomorrow and should be done…

Good Morning ILF, Hereby a short description of Jodans estimation, to complete construction of all intersections between – 3 July 2017 and 14 July 2017 Monday – Uranium/ Campbell rd intersection half width. Campbell no entry to Cedar Tuesday – Stinkwood/Cedar Avenue West intersection half width, Cedar west no entry to Cedar road Wednesday and Thursday…

After yesterday’s disaster with the traffic on Cedar Road the I Love Fourways team requested a meeting with Jodan Construction. While we could not get all our questions answered immediately this is what we have established. Communication: There is apparently a notification in circulation regarding the upgrades. We are unsure of the distribution of this…

So those who travel the Cedar Road route have all been facing the same nightmare every day for weeks now! As if the general delays in the area aren’t bad enough, the lights on Cedar Road are CONSTANTLY out and this is not only blood boiling for each of us, but its really bad for…