Direct message from Jodan Construction:

Good day to all

With the rain last week it placed us behind schedule and therefore no road closures will be done this week.

HOWEVER

Monday (16/10) and Tuesday(17/10) The final section of Cedar road will be paved as follow:
Valley intersection: Access to Broadacres will be available at all times. Please be alert as the entry and exit will be contra flow at the exit lanes.
The same scenario will be at Cedar Boulevard.
Jodan Construction thank all the motorist for their patience and even for those that had less patience. We hope that all will enjoy the road as all lanes will be open by next week Thursday.

Groete
James

 

 